Raising track embankment from 30m depth amid downpour a daunting task, say SWR officials
A stream changing its path following torrential rains on July 26 caused embankment erosion on valley-side on Sakleshpur-Subrahmanya Road Ghat stretch
Personnel from Mysuru Division of South Western Railway are tasked with raising the track embankment from a depth of 30 m on Sakleshpur-Subrahmanya Road Ghat section of Hassan-Mangaluru line near Kadagaravalli on Sunday.
| Photo Credit: SPECIAL ARRANGEMENT
Tasked with raising the embankment wall from a depth of 30 m and width of about 100 m for the Hassan-Mangaluru rail line in the Ghat stretch inaccessible by road has been a daunting task for the personnel of South Western Railway’s Mysuru Division.
While they struggle to raise the embankment with sand bags and boulders, rains lash the area making their task arduous. Yet, the men are working in shifts ever since the landslip was reported between Yadakumari and Kadagaravalli on Friday evening to restore the track. This is the first major landslip the ghat section is witnessing after the 2018 monsoon when landslips had occurred at 65 locations disrupting train traffic for nearly two months.
Control Room
The Division has established a control room from where the restoration work is being monitored live, said Additional Divisional Railway Manager E. Vijaya. Senior officers, including the General Manager, take turns to monitor the work and guide the teams on site.
Restoration plan
The restoration involves constructing a gabion wall and filling the area behind it with boulders and sandbags to make the required slope formation. Expert advice has been sought from multiple firms with relevant experience in similar restoration projects, said a release.
Out of the required 3,870 cubic metres of boulders, 670 have been unloaded and the remaining are being sourced. While 1 lakh sandbags of 40 kg each are required, 15,000 have been unloaded at site and the remaining are being arranged.
Equipment and machinery
The SWR has established a communication system, including auto phones, control phones, satellite phones, Wi-Fi and VSAT communication (for live streaming) for continuous monitoring and coordination from the war room at the headquarters in Hubballi.
Eight portable generators, over 60 floodlights, 8 torches, 10 extension boards, and 140 liters of petrol, along with gas cutters, are on-site to support the restoration efforts. Six earth movers and five excavators are working at the site, the release said.
Torrential rains
Ms. Vijaya said the stretch had received 230 mm rainfall on Friday, with over 100 mm being received within a couple of hours before the landslip occurred. A stream changing its path following torrential rains on Friday caused embankment erosion near a bridge on the valley side, she said.
Landslips were triggerred in August 2018 too after the region received very heavy rainfall, and excess to normal rainfall.
Strengthening works
After the 2018 major landslips and another minor one in August 2019, the SWR had initiated a slew of strengthening work on the 55 km stretch to protect the track from the hill as well as the valley side. This included the construction of catch and side drains, rockfall barriers, retaining walls, gabion walls, soil nailing, bridge strengthening etc.
Read Comments
- Copy link
- Telegram
READ LATER
Remove
SEE ALL
PRINT
Related Topics
Karnataka
/
Mangalore
/
rains
/
weather
/
Environmental disasters
/
natural disasters
/
disaster management
/
land resources
/
Roads and Rails
/
safety of citizens
/
communication infrastructure
/
Hubli